2011 Autumn / Winter Additional Work Programme

NOTE – No matter what other work is done the quality of the course is paramount and priority will always be given to presenting the playing surface in as good a condition as possible.

PLANNED WORKS


Complete the 11th newly constructed tees including final level and
turf.

Remove brushwood from top of the practice area between the 8th and
11th hole. Turf & seed new practice tee.

Verti Drain all the fairways, semi rough, and tees.

Excavate and construct a path from the 6th tee to the existing path that
runs down towards the 8th green.

Continue to blow leaves from the greens, fairways, and rough when
weather conditions allow.

Remove and replace damaged boards from paths and steps. Weed, refill
with path material and reconsolidate all paths with a very heavy roller.

Refill bunker sand in most bunkers.

Remove all dead trees on the course as per John Nicholson Report

Contractors are to remove trees on the 11th, 10th and 9th holes where
shading and overcrowding has taken place, as per Nicholson report.

Bunker edges and bare areas around the bunkers are to be re-turfed

Thin dense woodland if weather unsuitable for other on-course working

All greenkeeping machinery is to be serviced.


Course Manager
John Talbot